Serve notice of a claim on the prime contractor within
90 days of last performance or supply.
After 90 days, but within 1
year, of final acceptance
of the general contract.
Contracts less than $100,000 are excluded
from bond requirements on state projects. Discretionary
for the county, city or other subdivision of the
state if between $25,000 and $100,000.