California Private Time Frames

PrivatePublicSpeed BumpsWaiver WireFederal
Step 1 - Notice
  • Within 20 days of first furnishing.
  • A late notice may be served but will only retroactively trap 20 days from the date the late notice is served.
Step 2 - Lien
  • Within 90 days after completion of the entire work unless the owner has recorded a Notice of Completion or a Notice of Cessation. If either of these notices has been recorded the original contractor must file within 60 days after recording, other claimants must file within 30 days after the recording.
Step 3 - Foreclosure
  • Within 90 days of recording lien.

 

California Private Stop Notice Time Frames

 

Step 1 - Notice
  • Within 20 days of first furnishing labor or material.
Step 2 - Lien
  • After completion, and within 90 days of completion of the entire work, unless the owner has recorded a Notice of Completion or a Notice of Cessation. If either of these notices has been recorded, 60 days after recording for the prime contractor, and 30 days for all other lien claimants.
Step 3 - Foreclosure
  • Within 90 days of the last day to record the mechanics’ lien.

 